DEPARTMENT OF PLANNING AND ZONING – POLICY CHANGE FOR FINAL SUBDIVISION PLAT AND SITE PLAN APPROVAL
In the past the Department has verbally accepted an applicant’s
statement that the required plans and documentation have been submitted
and received by the Virginia Department of Health for soil work
approval for septic systems, the Virginia Department of Transportation
for entrance approval to a site and road design (if required), and the
Thomas Jefferson Soil and Water Conservation District Office for
approval of the Erosion and Sediment Control Plan and Storm Water
Management.
Effective immediately (February 23, 2006) this procedure has changed. The new policy and procedure of this office is as follows:
AT THE TIME OF SUBMISSION FOR FINAL APPROVAL OF A SITE PLAN OR FINAL
SUBDIVISION PLAT, AN ORIGINAL LETTER SIGNED BY THE APPROPRIATE AGENCY
REPRESENTATIVE MUST BE SUBMITTED STATING THAT THEY HAVE REVIEWED AND
APPROVED THE PLANS OR THAT THEY HAVE RECEIVED THE PLANS AND THEY ARE
CURRENTLY UNDER REVIEW.
IF THE PLANS ARE UNDER REVIEW, THE LETTER MUST GIVE PRELIMINARY
COMMENTS CON-CERNING THE PROBABILITY OF THE PLANS BEING APPROVED AS
SUBMITTED OR WHETHER SIGNIFICANT REVISIONS WILL BE REQUIRED.